Methodologies without dogma
Waterfall, Scrum, Kanban, Lean, PRINCE2: what they promise, when they work, how to choose. And why you choose the method for the project, not the other way round.
In the working world there are people who talk about methodologies the way others talk about football teams. The “agile” ones see planners as fossils; the planners see the agile ones as reckless amateurs. It is a debate that wastes a lot of time and has never finished a single project.
A methodology is a set of principles, rules and practices for organising work. Some are only principles (like Agile), others are complete systems of themes and processes (like PRINCE2), others again are bodies of standards (like the PMBOK) or simple processes (like Scrum). None is right in absolute terms. Each is right for something.
Before the method: the life cycle
Every project goes through five phases: initiation, planning, execution, monitoring, closing. What changes from one approach to another is how you go through them.
| Life cycle | How it works | When it makes sense |
|---|---|---|
| Predictive (waterfall) | The phases are crossed once, in order. Everything is planned at the start | Clear, stable scope, a single final delivery |
| Iterative | The phases repeat, and the solution is refined at each round | Scope isn’t clear, but you want to reach the best solution |
| Incremental | One working piece is delivered at a time, each complete | You need to deliver early, and the rest can wait |
| Agile (adaptive) | Iterative plus incremental: short cycles, each with its own feedback | Change is likely and feedback is essential |
| Hybrid | Approaches are combined, phase by phase | Almost always, in real life |
The most widespread methodologies
- Waterfall. Detailed planning, sequential phases, documentation. It promises predictability on time, cost and scope. It works when requirements are stable; it suffers when they change halfway.
- Scrum. A small, cross-functional, self-organising team working in short cycles (sprints, usually one to four weeks), starting from a prioritised list (the backlog) and closing each cycle with a review and a retrospective. It works when you can deliver in pieces and the client takes part; it hollows out when only the ceremonies remain.
- Kanban. Makes the work visible on a board, limits work in progress, improves flow. It has no fixed cycles: it is ideal for continuous work, like a creative department that receives requests every day.
- Lean. Eliminate waste, maximise value, keep improving. It is more a philosophy than a method, and it was born on the factory floor, in the Toyota Production System.
- PRINCE2. Defined stages, roles and responsibilities, constant control: PRojects IN Controlled Environments. It works in large organisations and in projects where every step must be accounted for.
- Crystal. People and interactions at the centre, rules adapted to the size and criticality of the project.
The agile manifesto, in brief
In 2001 seventeen software developers signed the Manifesto for Agile Software Development. It says it values individuals and interactions over processes and tools, working software over comprehensive documentation, customer collaboration over contract negotiation, responding to change over following a plan. And it adds a sentence the fans often forget: while there is value in the items on the right, the items on the left are valued more. It is not a manifesto against planning: it is a manifesto about priorities.
How to choose
Before choosing a method, it pays to ask six questions about the project.
| Question | If the answer is… | …it leans towards |
|---|---|---|
| Is the scope defined and stable? | Yes / No, it will change | Predictive / Adaptive |
| Is the team large or small? | Large, with different roles / Small | Predictive / Adaptive |
| Does the client take an active part? | Only at the start and end / Yes, often | Predictive / Adaptive |
| Is the budget fixed? | Yes / There is flexibility | Predictive / Adaptive |
| Are the deadlines rigid? | Yes, with a single delivery / We can deliver in releases | Predictive / Adaptive |
| Can we think in terms of an MVP? | No, everything is needed at once / Yes, we start from the essentials | Predictive / Adaptive |
The answers rarely all point the same way. That is where the hybrid approach comes from, and it is the rule rather than the exception. A common example in agencies: contract, scope and main milestones managed predictively, because the client needs firm dates and costs; production organised in sprints, with frequent reviews; ongoing requests and small maintenance handled on a Kanban board.
The most common mistakes
- Method as identity. When a team defends its method more than the result, it has stopped working for the project.
- Ceremonies without substance. Stand-ups, sprints and retrospectives held out of habit, without anything changing. Agile in name only.
- Method as an instrument of power. Rules used to control people, not to help them work.
- The rigidity of those who foresaw everything. In Waterfall, anything that wasn’t foreseen becomes a weak point. The plan is needed; the unexpected comes anyway.
- Switching method halfway without saying so. The client thought they were buying a defined result and finds themselves inside an iterative process, or vice versa. The methodology must be declared, in the Statement of Work.
Learning from mistakes, together
The last thing methods have in common is the most important: they only work if you look back. Retrospectives, debriefs, lessons learned: whatever you call them, they are the moment when a team decides what to keep and what to change. That is where a method stops being a dogma and becomes a way of working.
The right questions
- Are we choosing the method for the project, or the project for the method?
- What do we really need from Scrum, Kanban or Waterfall in this case?
- Does the client know which approach we work with, and is it written down?
- Do our ceremonies change anything, or are they a habit?
- Where do we collect what we learn from our mistakes?
In the book
I’ve never been a fan of fights between approaches to prove one’s own is better than the others.
Gordon Wayfarer, p. 197
In Breakdown New Elysium is divided into castes, and each has made a methodology its identity: Scrum, Waterfall, Kanban, Crystal, PRINCE2. When Lean becomes an instrument of power, Gordon foils a coup with allies from different castes. In the end the city rebuilds itself without dogma, and a Council of Methods is founded to document what everyone learns from their own mistakes.
Methodologies compared No method is dogma Case 07 · Breakdown
Quotations from the novel are translated from the Italian edition. Page numbers refer to the Italian edition.
More guides
For people who run projects
What a project manager really does
Not an air traffic controller, but one of the most creative jobs there is. What a PM does, why the role matters, how you become one.
For people who run projects
From brief to Statement of Work
Requirements, brief and SoW: who writes them, what they must contain, how to receive them. And when it makes sense to go beyond the brief.
For people who run projects
Starting well: kick-off and alignment
Objectives you can measure, a kick-off that isn’t a formality, the calendar of alignment meetings.